Certificate of Approval for the Feasibility Study of the Electrical Transmission Lines
ໃບຢັ້ງຢືນເພື່ອຮັບຮອງບົດວິພາກເສດຖະກິດ-ເຕັກນິກໂຄງການສາຍສົ່ງໄຟຟ້າ
General information | ||
---|---|---|
Type of formality | Certificate | |
Date of last modification | 15.10.2020 | |
Responsible Authorities | Department of Energy Policy and Planning
|
|
LSIC | D - Electricity, gas, steam and air conditioning supply | |
Who should complete this business formality? |
Any individual or legal entity intends to operate a hydropower business |
|
Qualifications needed by the business to get the formality |
Operating in accordance with the terms of reference (TOR), guidelines, electricity laws, electrical technical standards, and fees set by the Ministry of Energy and Mines. |
|
Additional Comment |
REQUIRED DOCUMENTS FORMALITIES - First time | ||||
---|---|---|---|---|
Name | Comment | |||
Feasibility Study | of the project |
REQUIRED DOCUMENTS FORMALITIES - Renew | ||||
---|---|---|---|---|
Name | Comment |
Mean of presentation | ||
---|---|---|
Means of presentation | At the Authority Offices | |
Address of authority | Department of Energy Policy and Planning, Ministry of Energy and Mines | |
Processing Time (Day(s)) | 20 | Within 15-20 working days |
RENEWAL INFORMATION | ||
---|---|---|
Does the formality have a validity or an expiration date? | NO | |
How long will the formality be valid for? (in months) | 0 | |
What is the process and conditions to renew the formality? |
ISSUING FEES | ||||
---|---|---|---|---|
Has application fees? | Service fees | Certificate fees | Application fees | Total fees |
YES | 0.00 | 0.00 | 0.00 | 0.00 |
Comments |
The service charge for the information: - The copy of the information A4: 30,000 LAK/page - The copy of the information A3: 40,000 LAK/page - The copy of the technical information: 200,000 LAK/set Moreover, the collection of fees for the issuance of a certificate of the feasibility study of the electrical transmission lines is charged in accordance with the size of the project: 1. Medium-scale project 22 KV and small-scale project 0.4 KV: 500,000 LAK 2. Medium-scale project 115 KV: 800,000 LAK 3. Medium-scale project 230 KV: 1,000,000 LAK 4. Medium-scale project 500 KV: 1,200,000 LAK |
RENEWAL FEES | ||||
---|---|---|---|---|
Has renewal fees? | Service fees | Certificate fees | Renewal fees | Total renewal fees |
NO | 0.00 | 0.00 | 0.00 | 0.00 |
Comments |