Construction Permit
ໃບອະນຸຍາດປຸກສ້າງ
General information | ||
---|---|---|
Type of formality | Other | |
Date of last modification | 11.01.2018 | |
Responsible Authorities | Public Work and Transport Department
|
|
LSIC | All sectors | |
Who should complete this business formality? |
Individual or legal entity intends to construct the building or other construction which comprise of: 1. Construction and Installation; 2. Expansion and Changes in usage goal; 3. Restoration and Renovation; 4. Demolish and Restoration |
|
Qualifications needed by the business to get the formality |
1. The construction design must be in accordance with technical standards and comply with the city map and relevant regulations such as master plan, zoning map, and regulation on using specific land including the regulation on the Management of the City and Construction, architectural conservation, environment, and others. 2. Must have Land Title. 3. For those who have land-use right but the Land Title Project has not gone there yet [the authority] will consider on a case by case basis. |
|
Additional Comment |
1. Provincial Governor Administrative Office/Vientiane Capital is the authority to give approval on building level 1 which comprise of a big building with an area of 10,000 square meters, the height is more than 20 meters, it is a controlled building, Industry and Handicraft Factory Plant level 3 and 2, the construction with environmental impact. 2. The Department of Public Works and Transport of provincial is the authority to give approval on building level 2 which comprise of the medium building with an area of 400 to 10,000 square meters, the height is more than 10 to 20 meters, fuel station in all level, Industry, and Handicraft Factory Plant level 1, construction with environmental impact, telecommunication and communication tower systems, large power pole, large billboard (all types of LED, roadside signage size 2x4 meters and over). 3. Office of Public Works and Transport is the authority to give approval on building construction level 3 which comprise of a small building for a resident with an area, not more than 400 square meters, the height is not more than 10 meters, and small roadside signage (not more than 2x4 meters). The relevant authority will inspect the building that they have granted the approval at least 2 times before the completion of the building. After the building is completed the applicant must notify the authority not later than 15 days in order to have a final inspection and issue the accuracy certificate as evidence until such building is changed. |
LEGAL FRAMEWORK | ||||
---|---|---|---|---|
Name | Number | Date | Comment | |
Law on Urban Planning (Amended) | 40/NA | 16.01.2017 | ||
Law on Construction | 05/NA | 26.11.2009 | ||
Decision on the Management of Construction Activity | 2241/MPWT | 31.01.2019 |
REQUIRED DOCUMENTS FORMALITIES - First time | ||||
---|---|---|---|---|
Name | Comment | |||
Land Title | prepare 3 copies in the size of F14 |
|||
Copy of ID | or Family Registration Book or Passport (for foreigner) |
|||
Project Diagram | including the Diagram of the Aerial View of the location (ratio 1/5000), the Overall Diagram, the Diagram on Land Management, Sections compared to the land size, Diagram of the Drainage System, Diagram of Wastewater Treatment Plan, Architecture Model, Building Plam and other related systems |
|||
Certified Project Diagram | from a Housing Construction (Survey-Design) Company that has a Business Operating License |
|||
Request Letter |
REQUIRED DOCUMENTS FORMALITIES - Renew | ||||
---|---|---|---|---|
Name | Comment |
Mean of presentation | ||
---|---|---|
Means of presentation | At the Authority Offices | |
Address of authority | Public Work and Transport Department, Vientiane Capital | |
Processing Time (Day(s)) | 45 | After receiving the application, the authority will inspect the construction site and in case the design is incorrect or some documents are not detailed or not meet the standard, the Construction Management Organization will inform the applicant within 7 days, if the application is completed [the authority] will issue the permit not more than 30 days from receiving of application. |
RENEWAL INFORMATION | ||
---|---|---|
Does the formality have a validity or an expiration date? | YES | |
How long will the formality be valid for? (in months) | 6 | |
What is the process and conditions to renew the formality? | This permit is valid for 6 months from the date of signing. In case there is no construction during such a period, the applicant can renew one time. If the permit exceeds the expiration date, the permit will not be valid. |
ISSUING FEES | ||||
---|---|---|---|---|
Has application fees? | Service fees | Certificate fees | Application fees | Total fees |
YES | 50000.00 | 150000.00 | 0.00 | 200000.00 |
Comments |
The fees are based on the recommendation from the authority. |
RENEWAL FEES | ||||
---|---|---|---|---|
Has renewal fees? | Service fees | Certificate fees | Renewal fees | Total renewal fees |
YES | 50000.00 | 150000.00 | 0.00 | 200000.00 |
Comments |
The fees are based on the recommendation from the authority. |